Work Plan (Drafts)

Outline (v.2)
Budget (v.2)
Schedule (v.2)

Electronics Web Site

Engineering Drawings (25 June 2005)

Sling Drawings (4 August 2005)

Photos of Fabrication
9/28/04
Instrument Shop

Electronics Shop

4/13/05
ADC on lift

10/26/04
Instrument Shop

6/17/05
Model and Jackstand being shipped to Keck

11/2/04
Instrument Shop
8/15
Prisms being prepared for delivery to LLNL for sol-gel coating
12/3/04
Instrument Shop: Rail, Jack Stand
8/17/05
Prism handling
12/13/04
Instrument Shop
10/2-3/05
Prism Installation
1/28/05
Instrument Shop
 
2/3/05
Instrument Shop
 
2/10/05
Optics Shops
 
3/9/05
ADC with Dummy Optics
 

 

 

 


 

About ADCMonthly ReportsCurrent DrawingsParticipants

 


Project Phases


Phase A
Preliminary Design
Detailed Design
Fabrication and Assembly
Testing
Pre-Ship
Shipping
Installation
Commissioning

 

 

 

 

 